Project Update
| |
|
Action |
Target Completion |
Status |
|
Project Start up (April 2003) |
|
Complete |
|
Resource
Consents original |
|
Complete |
|
Legal Arrangements |
|
Trust established |
|
Access road |
|
Completed |
|
Lake transfer |
|
Shifted to adjacent property |
|
Technical design and working drawings, KartSportNZ
approval |
July 2006 |
Completed |
|
CIK assessment |
November 2006 |
Step 1 (simulation) completed. |
|
Subdivision and Land Purchase |
November 2007 |
Subdivision approved, S & P signed, waiting on
title |
|
Preliminary earthworks and drainage |
December 2007 |
Completed |
|
Major Circuit earthworks |
April 2008 |
Completed |
|
Surface drainage |
May 2008 |
Completed |
|
Track sealing |
February 2009 |
Completed |
|
Driver training programme |
March 2009 |
First partner, RYDA ,established |
|
Services |
October 2009 |
|
|
Sealing Pit area |
Third quarter 2009 |
|
|
Complete Sub Division & Title |
November 2009 |
|
|
Safety Fencing |
Third quarter 2009 |
|
|
Club Racing starts ?? |
Fourth quarter 2009 |
|
|
Construct Control Tower & Systems |
Fourth quarter 2009/First quarter 2010 |
|
|
Pavilion/ training centre |
First quarter 2010 |
|
|
Complete car parks/ landscaping |
First quarter 2010 |
|
|
CIK Inspection |
tba |
|
|
Regional/ major events |
Third quarter 2010 |
|
|
Rotax Max World Championship ? |
November 2011 |
Application underway |
|
|
Just $3,400,000 TO BUILD this fabulous
TRACK and facilities
| $2,530,800 raised
! |
Funds
for completion: $869,200 |
News & Pictures
- December 2007 -We welcome new partners Rotorua Energy
Trust who have made a major contribution to this exciting community
project and Bay Trust who have contributed a very worthwhile level
of support to a Bay of Plenty asset. The Lion Foundation have again
reinforced their belief in this project with a further grant.
- Site cleared, major drainage pipes
installed, major earthworks progress, 2 way access road built and
metalled.
- Resource consent extension and freehold
subdivision (approved) being processed.
- February 2008. We appreciate the decision
by The Southern Trust to join us as partners and help drive the
earthworks towards completion.
- February 2008. Rotax International
expressing interest in holding a World Championship in New Zealand.
- May 2008. Publicity Day held for partners and
other interested parties. Thanks to Rotorua Energy Trust for helping
with the expenses on the day and Off Road NZ for the use of the Bush
Camp and those nifty Suzukis.
- May 2008. First Sovereign swings in behind us
again with a grant towards the surface drainage.
- June 2008. First Sovereign strengthened their
partnership with a further grant enabling us to complete the surface
drainage. (Now well tested!)
- July 2008. New Zealand Community Trust
(NZCT) provide great contribution for finalising stage 1 earthworks.
- October 2008 Great news from The Lion Foundation
with significant support enabling the sealing contract to proceed to
negotiation and more - a grant for the design and specifications for
the Control Tower. This building is a must have for the control of
all race day activities.
- December 2008 Yah! DownerEDIWorks join us
as a partner and preparation for sealing begins.
- December 2008 First Sovereign - back to help us
and this time toward the important circuit sealing stage.
- February - Happy New Year and a great milestone -
preparation and asphalting of the track completed on the 5th
February. Looks a great job.
- April 2009 - a great month. Rotorua District
Council and Hayes International join at the corporate partner level
and really boost our progress. Their support will achieve more than
half the Control tower. NZCT provide further financial support
for the sealing stages. Local companies Aries Construction,
Andersen
Drainage, Temprite Industries, Hickey Construction and
Wilco
Products chip in to move the Control Tower further forward.
- April 2009 - Our Patron Greg Murphy is the first
to test the track and loves it.
- August 2009 - The Lion Foundation lend yet
another great helping hand to advance our preparation for sealing
the pit area.
- October 2009 - The Southern Trust bring
wonderful support enabling the contract for pits sealing to go
ahead. This will provide the on and off track pit lanes, the
pits area surrounding the Control Tower and the driveway down from
the upper level car park into the pits area.
- October 2009 - Unison - The Powerlines
People - join us as a Project Partner and greatly assist us in
arranging for the kilometre of power line that will bring the energy
to all those computers, lights, kitchens etc, etc to make this
sporting complex work.
- November 2009 - With the winter behind us we have
reshaped some of the infield swales to work better with the drainage
system. This has been followed by grass seeding and now we want
those gentle warm rains please!
|
|
|

Aerial view of the Rotorua KartSport track site -before
sealing |

In the beginning |
|
I 
First layer of asphalt on top of sealed base.
Second layer (Infratrac) being laid. Tandem laying, hot middle join.
|
|
 
Boys and Girls and our Partners are raring to go -
Greg Murphy tests the track
We just
need to finish the construction!

1.2km of excitement and sport. The naming rights are still available - what an
opportunity.
Thanks to Bill Mason for photos |